Here at Below Ground we are very proud of the high-quality drainage and water works that we have carried out. Below are some report and photos of a selection of jobs that we have carried out recently.


Treatment Plant Installation in Somerset

POSTED: April 30, 2019

Date: 01/04/2019 -05/04/2019 Site Address: North Curry, Somerset Works: Treatment plant installation Report: Below Ground Solutions have recently finished carrying out a treatment plant installation in Somerset. These installation works provided us with a challenge due to the site’s unique priorities, we sent our lead engineer Lee to site to asses the needs of our customer. While on this site visit, we spoke to our customer to confirm his needs and why they wanted to go down the...

Read in full »

New Foul Sewer Connection in Essex

POSTED: March 13, 2019

Date: 06/03/2019-08/03/2019 Site Address: Bishops Stortford, CM22 Works: Foul Water Sewer Connection Report: This project came to us via our website after our customer was having troubles with his existing septic tank. On our first visit to site we were tasked with inspecting the current drainage system at the property, and after a confirmed space team entered the customer’s septic tank. We concluded that the tank was such a poor condition that the best course of action...

Read in full »

Sewage Treatment Plant installed in The New Forest

POSTED: February 08, 2019

Date: 04/02/2019 -07/02/2019 Site Address: West Common Blackfield, SO45 Works: Treatment plant installation Report: After some recent bad luck with his septic tank failing, we at Below Ground Solutions installed a sewage treatment plant for this very happy customer: “After failure of our old original above ground brick constructed septic tank I was forced into replacing it. Much research & time was invested into which system to install & which company could do the job...